76 Balancing
BALTECH VP-3470
Operation manual
Figure 78. Manual input, step 1
2. Press Enter to move to the PEAK AND PHASE (Figure 78). 
Figure 79. Manual input, step 2
3. Perform the actions described in the p, 2-11 to carry out the single –plane
balancing  (9.1.NEW  BALANCING).  The  vibration  phase  and  amplitude  must  be 
entered manually.
9.3. Re‑balancing
If you have already made the balancing of the machine and you have got the
balancing reports we recommend that you perform the scheduled balancing of this
machine using RE-BALANCING.
To perform the re-balancing install the tachometer at the same place as it was
installed during the balancing. Check the location of the reflective mark (it should 
be the same).     