1.4
Positioning
l For installation choose the most suitable position for steam distribution, that is, the position that
minimises the length of the steam pipe. The unit has been designed to be floor standing, on a base
that supports its weight in normal operating conditions (see the table of “Dimensions and weights”).
l The metal casing of the humidifier heats up during operation, and the top part may reach
temperatures > 60°C (140°F); therefore make sure that this does not cause any problems.
l Make sure the humidifier is level, and that the minimum clearances are respected, as shown in the
figure below, to allow room for maintenance operations.
Important: make sure that the combustion air intake grille is not blocked or covered.
Fig.1.b
1.5 Opening
1.5.1 Front panel
Unscrew the screws using a Phillips-head screwdriver (A), grasp the handles and slide the panel slightly
downwards to remove it.
Fig.1.c