Chore-Tronics® 2 Control Control Installation
MT1843B
89
Testing the Back Up Box
To test the Back Up Box, first turn the power off to the Chore-Tronics
®
2 Control
only. This should cause the Tunnel Curtain to open and the first set of Back Up Fans
should activate. If this test is successful, turn the power back on to the Chore-
Tronics
®
2 Control. Then adjust thermostat number one until it activates. Then adjust
the second thermostat until it activates. This should cause the second set of Back Up
Fans to activate. After all Back Up Fans are operating, deactivate the first two
thermostats. Than adjust the third thermostat until it activates. This should cause the
Back Up Heaters to activate.
After all of the outputs and back ups have been successfully tested, make sure all
manual toggle switches are in the manual "off" position and proceed to the "Initial
Set Up" portion of this manual beginning on Page 46.
Wiring of Outputs
The outputs for the Chore-Tronics Controls (Fans, Curtain Machines, Brooders,
etc.) are wired to one of the Relays on the Relay Module or (RM Board(s). The
RM Board consists of eight 1hp motor load Relays. Each Relay has single-pole,
single-throw normally open contacts. It is strongly recommended that the
assignment of outputs to the Relays be done before starting to wire the Control.
This will make routing of the electrical wires through the Relay box much easier
(See Figure 106).
The appropriate output stickers should be placed over the toggle switches used,
if it has not already been done prior to mounting. Please see the wiring diagrams
on the following pages for wiring Chore-Time ventilation equipment. (Wiring
diagrams for Fans, Linear Lifts, Super Lifts, Brooders, Turbo Cool, Mister Cool).
For other types of equipment please refer to wiring diagrams supplied with the
equipment.
Mt1701-038 2/02
Feed Cl ock
Figure 106. Relay Assignments