7.6.2.3 Priorities
The priority of the gen-set within the group is given by the setpoint Pwr management: Priority. Lower
number represents "higher" priority, i.e. a gen-set with lower number starts before another one with
higher number. In other words, the setpoint Pwr management: Priority means order in which gen-sets
are started and connected to the bus. An example is shown on the figure below. There are four gen-
sets with following choice of setpoints:
Power [% / kW]
Sum of available nominal
power – running gen-sets
in PM
Total load of the system
Level to start additional gen-
set Nom Pwr - #LoadResStrt X
Level to stop additional gen-set
Nom Pwr - #LoadResStop X
130
330
150
350
400
Time
Time
Starting
sequence
Gen #4 Priority = 1
Gen #3 Priority = 2
Gen #2 Priority = 3
Starting sequence
Stopping sequence
200
330
350
400
800
Gen #1 Priority = 4
Starting
sequence
Starting
sequence
Stopping
sequence
Stopping
sequence
Stopping
sequence
Figure: Power management example - Priorities