11
I. Lay a concrete slab 400mm x 400mm x 200mm:
• Dig a hole and place the conduit ❶ in the correct
posion.
• Fill the hole with concrete & allow to set.
II. Place the foundaon plate on the concrete slab &
feed the conduit through the cable inlets ❷.
III. Ensure a 23mm clearance between the inner
edge of the foundaon plate and the edge of the
gate. This measurement is based on DACE rack.
See below to calculate clearance if using other
rack.
IV. Aach the foundaon plate to the slab using four
8mm anchors ❸.
ANCHORING THE FOUNDATION PLATE
Open the ‘manual release door’ and pull the
release pin unl the lid is free. The Lid can now
be removed.
REMOVING THE LID
1. Open the ‘manual release door’ and rotate the thumb
wheel clockwise, just unl the gate begins to move.
2. The thumb wheel must not be allowed to rotate too far.
3. To re-engage the gearbox, rotate the thumb wheel
counter clockwise while pushing on the gate unl you
hear a click in the gearbox.
4. Do not rotate the thumb wheel any further aer hearing
the gearbox click.
PLACING THE OPERATOR IN MANUAL OVERRIDE
To calculate the clearance required between the edge of the
foundaon plate and the edge of the gate (A), measure the
width of the rack (B) and minus 9.
eg. If the width of the rack is 32mm less 9 = 23. Thus the
clearance required is 23mm
Side view
Gate
Rack
Foundaon
Plate