For the SHORE connection controller:
1. Deactivate switchboard control. Press LOCAL so that the controller is in LOCAL mode.
2. Press Close breaker
. Do the GENSET controllers with external set point (network) activated synchronise the busbar
to the shore connection? Is the synchronisation fast enough?
3. When the breaker closes, press Open breaker
. Do the GENSET controllers with external set point (network)
activated de-load the breaker? Does the breaker open?
7.3.2
SHORE connection controller functions
Functions
Synchronisation and de-
loading
• Broadcast the set point for GENSET controllers
Counters
• Display unit counters, to edit or reset
◦ Breaker operations and trips
◦ External breaker operations
◦ Power export (active, and reactive)
◦ Power import (active, and reactive)
• Energy counters with configurable digital outputs (for external counters)
◦ Power export (active, and reactive)
◦ Power import (active, and reactive)
7.4 BUS TIE breaker controller
7.4.1 Basic BUS TIE breaker controller tests
After completing the previous commissioning steps, the BUS TIE breaker controller should have the correct protections and
parameters. The breaker close and open should function correctly.
This section describes some basic tests for the BUS TIE breaker controller.
The complete list of BUS TIE breaker controller functions is also given below. As relevant, test these functions in the system.
Basic BUS TIE breaker controller tests
DANGER!
Complete all the previous commissioning steps before performing the basic BUS TIE breaker controller
tests.
For each BUS TIE breaker controller:
1. Deactivate switchboard control. Press LOCAL so that the controller is in LOCAL mode.
2. Press Close breaker
. Do the GENSET controllers with external set point (network) activated synchronise the
busbars? Is the synchronisation fast enough?
PPU 300 Commissioning guidelines 4189341106 UK
www.deif.com Page 61 of 75