3. Select Tools > Report .
4. Make sure all features are selected.
5. Select Print
in the right side panel.
• PICUS creates a report from the features selected.
6. Use Print to print the report from your computer and Close to return to PICUS.
See Report in the PICUS manual for more information about creating the report.
8.1.2 Finalising the operator's manual
Ensure that the operator's manual is updated for the system's configuration, the switchboard design, each controller's
hardware configuration and parameters, and the system-specific CustomLogic. Make sure that the operator's manual is
accessible, and that a copy of the updated operator's manual is stored in a safe place.
8.1.3
Finalising the commissioning report
The commissioning report is a record of the actions taken to commission the equipment. It should be based on the detailed
commissioning plan. Complete this report, and file it in a safe place.
8.1.4 Commissioning checklist
Applies to Description Notes
General Commissioning personnel are qualified and experienced.
General The tools for commissioning are available and ready.
General
System design is complete.
The settings (including the single-line drawing, the controller input/
output connections and functions, the controller parameters, and
CustomLogic) are saved to the controllers.
General The switchboard is built. The controllers and display units are installed.
General
The switchboard and controllers have passed the factory acceptance
test (FAT).
All controller types The breaker(s) are disabled.
GENSET controller The engine start is disabled.
Each controller
The controller power supply is connected, and the controller LEDs are
checked.
Each controller The Ethernet communication is checked.
Each controller The display unit is checked.
Each controller The protection parameters are checked.
Each controller The controller safety (emergency stop, shutdowns, trips) is checked.
Each controller The system and alarms are checked.
GENSET controller
With the breaker open, the gensets are started, stopped, and run
under switchboard control.
PPU 300 Commissioning guidelines 4189341106 UK
www.deif.com Page 65 of 75