Applies to Description Notes
Each controller The phase sequence is checked.
Each controller The breaker open and close is checked.
Each controller
Under switchboard control, synchronisation and de-loading are
checked.
GENSET controller The speed droop is checked, and adjusted if necessary.
GENSET controller The voltage droop is checked, and adjusted if necessary.
GENSET controller The regulators are tuned.
Each controller Controller functions are checked.
Each controller LOCAL and REMOTE operation modes are checked.
The system Customised sequences (CustomLogic) are checked.
The system Failure scenarios are checked.
Each controller The controller settings are backed up.
The system The operator's manual is updated.
The system The commissioning report is finalised.
The system The commissioning checklist is completed.
PPU 300 Commissioning guidelines 4189341106 UK