48 Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
Figure 33. Rail Screw Positions for the EBM Bottom Installation
Position 1
Position 6
Position 10
Position 15
First Rail
Second Rail
Rear Rail Screw Positions
(Installed at Bottom of Rack)
Front Rail Screw Positions
(Installed at Bottom of Rack)
Position 2
Position 4
Position 11
Position 13
First Rail
Second Rail
3. Secure the rail to the front of the rack with two hex-head screws ( see Figure 34) .
Figure 34. Securing the Front Rail
4. Using two clip nuts and two hex-head screws, attach the rail to the rear of the rack (see Figure 34 and
Figure 35 ).
The bottom rail uses positions 38 and 40 for the rear hex-head screws. If you are installing additional rails,
place the next rail 7 holes above the last installed screw.
Rack Setup for the EBM