SEP 2005 MODEL 1000
INSTALLATION AND SETUP
3-48
Figure 3-8. Separate Conduit Entries
To connect serial communications lines to the GC Controller, follow these steps:
(1) Access the GC Controller's Terminal Board for Field Wiring (TB).
(a) If necessary, see instructions in Section 3.4.1, step (1).
(2) Route serial communications lines appropriately, especially in the case of the explosion-
proof Controller enclosure.
(3) Make serial communications line connections to the GC Controller TB. The port numbers
and pinouts are listed in the following "...Serial Specifications" Sections (3.4.4.1 through
3.4.4.3).