3.4.7 Analog I/O Wiring
4
Install Analyzer Wiring
5
Install Analyzer Sample & Gas Lines
6
Install GC Controller Wiring
»
7
Perform Leak Checks
To connect analog signal input/output lines to the GC Controller, follow these steps:
(1) Access the GC Controller's Terminal Board for Field Wiring (TB).
(2) Route analog I/O lines appropriately. Refer to drawing DE-20782.
(3) Make analog I/O connections to the GC Controller TB. In standard configuration, there are
connections for four analog input and two analog output lines, as follows:
(a) Analog Inputs - GC Controller TB, connection port "J12"
Analog Outputs - GC Controller TB, connection port "J14"
(b) For specific pin number assignments, see drawing DE-20782, GC Controller
drawings addendum, this manual.