Proline Promass E 100 Modbus RS485 Commissioning
Endress+Hauser 49
10 Commissioning
10.1 Function check
Before commissioning the device, make sure that the post-installation and post-
connection checks have been performed.
• "Post-mounting check" checklist → 23
• "Post-connection check" checklist → 34
10.2 Establishing a connection via FieldCare
• For FieldCare connection
• For establishing a connection via FieldCare → 42
• For FieldCare user interface → 43
10.3 Configuring the measuring device
The Setup menu with its submenus contains all parameters needed for standard
operation.
Structure of the "Setup" menu
Setup
→
System units
→ 49
Select medium
→ 52
Communication
→ 53
Low flow cut off
→ 55
Partially filled pipe detection
→ 56
10.3.1 Setting the system units
In the System units submenu, you can configure the units of all measured values.
Navigation path
"Setup" menu → Advanced setup → System units
Structure of the submenu
System units
→
Mass flow unit
Mass unit
Volume flow unit
Volume unit
Corrected volume flow unit
Corrected volume unit
Density unit
Reference density unit