Endress+Hauser 3-1
3 - INSTALLATION
This chapter describes the processes used to mount and install your SS2100
H
2
S analyzer. Once the system arrives, you should take a few minutes to
examine the contents before installing the unit.
What Should be Included in the Shipping Box
The contents of the crates should include:
• The Endress+Hauser SS2100 H
2
S analyzer with SCS
• A document CD, which includes this manual and other system
manuals and documents
• One external serial cable
• Additional accessories or options as ordered
If any of these contents are missing, refer to “Service” on page B-25.
Inspecting the Analyzer and SCS
Remove top and sides of crate and carefully inspect all enclosures for dents,
dings or general damage. Inspect the supply and return connections for
damage. Report any damage to the carrier.
Each analyzer is configured with various accessories and options. If there is any
discrepancy in your order, please refer to “Service” on page B-25.
Endress+Hauser Class 1 Division II analyzers use a non-incendive
protection method, and as such all portions of the local installation
codes apply. The maximum allowed inductance to resistance ratio
(L/R ratio) for the field wiring interface must be less than 25
µH/Ω. The maximum total loop capacitance shall be 0.27
microfarads.
The safety of the analyzer is the responsibility of the installer and
the organization he/she represents.
Avoid jolting the instrument by dropping it or banging it against a
hard surface which may disturb the optical alignment.