EasyManua.ls Logo

Fujitsu ETERNUS LT40 S2 - Figure 2.9 Setting in the Right Rail at the Front; Figure 2.10 Screwing on the Right Rail at the Front

Fujitsu ETERNUS LT40 S2
110 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Chapter 2 Installing the Tape Library
2.5 Rack Mounting the Library
FUJITSU Storage ETERNUS LT40 S2/LT60 S2 LTO Library Installing, Starting Up and Maintaining
Copyright 2018 FUJITSU LIMITED P3AM-5392-07ENZ0
29
4 Compress the spring mounted rail to its length, putting the preloaded screw head in the
lower front lug of the rail from behind into the appropriate hole of the right front rack post
as shown below.
The rail now is positioned between the two rack posts by its spring pressure. Support the rail with one
hand.
Figure 2.9 Setting in the right rail at the front
5 Screw on the upper lug of the front rail end to the right front rack post using one screw with
centering washer as shown below.
Figure 2.10 Screwing on the right rail at the front

Table of Contents

Related product manuals