GE HEALTHCARE
DIRECTION 5245279, REVISION 3 LOGIQ™ P6/P6 PRO SERVICE MANUAL
Section 8-2 - DISASSEMBLY/RE-ASSEMBLY 8 - 83
8-2-37 Cup Holder
8-2-37-1 Tools
No need tool
8-2-37-2 Removal procedure
1.) Remove the cup holder. Refer to the figure below.
2.) Perform the following functional tests. If all are successful, include the debrief script provided below.
8-2-37-3 Mounting Procedure
Install the new parts in the reverse order of removal.
Figure 8-125 Cup holder
Table 8-38 Functional Tests
Service Manual
Section
Functional Test / Diagnostic Test Debrief Script
Section 4-3-1
Power On/Boot Up
“Service Manual, Direction
5245279, Rev 3+, Section 8-2-37. Equipment
passed all required tests and is ready for use. “
Section 4-3-2
Power Off / Shutdown
Section 4-8-4
Cup holder Function Validation Procedure
Section 10-5-5
Physical Inspection