Preface
1–6 INS 61301607027 Rev A US
HOW TO USE THIS MANUAL
PLAN THE INSTALLATION Ensure all installation requirements have been met:
1. Review the Installation Drawings (Section 6) and architect’s drawing.
2. Review the Technical Data (Section 7) for steam supply and steam
boiler feedwater quality recommendations.
INSTALL THE EQUIPMENT Install the sterilizer as follows:
1. Unpack the sterilizer.
2. Remove the sterilizer from the skid, then roll the sterilizer to the room
where it will be located.
3. Position and level the sterilizer.
4. Connect the plumbing.
5. Connect the wiring.
6. Install any remaining optional equipment.
7. Anchor the sterilizer.
8. Install the optional cabinet package.
9. Perform the functional check.