Installation Instructions
4–28 INS 61301607027 Rev A US
INSTALLING THE SEISMIC
ANCHORING BRACKETS
If seismic anchorage is required per local codes, all four leveling feet must
be anchored (see Figure 4–25). Four bolts per corner are required to meet
seismic anchoring codes.
NOTE
The anchoring specifications recommended in this manual (see seismic
anchorage drawing on page 6–10) are in compliance with seismic
anchoring codes set forth by the state of California.
It is recommended that permanent anchoring of the sterilizer to the floor be
done after the unit has been checked out by a qualified Getinge USA
service representative.
FIGURE 4–25. SEISMIC ANCHORING BRACKETS
NOTE
The holes cannot be drilled with the sterilizer in place because of
interference with the sterilizer frame. If the holes are not already drilled, it
will be necessary to mark the holes, move the sterilizer out of the way, drill
the holes, then move the sterilizer back to its location.
The casters must be removed to allow the seismic anchorage brackets to
anchored in four places.
A07027-T2
Leveling Bolt
(4 places)
Front Bracket
Rear Bracket
Sterilizer Frame
(Top View)