Installation Instructions
4–26 INS 61301607027 Rev A US
ANCHORING THE STERILIZER
The sterilizer is anchored to the floor with two hold-down brackets as
shown in Figure 4–24 on page 4–26.
NOTE
If seismic anchoring is required by local codes, the sterilizer is anchored as
described in “Installing the Seismic Anchoring Brackets” on page 4–28.
INSTALLING THE HOLD-DOWN
BRACKETS
To install the hold-down brackets:
1. Remove the brackets and hardware from the small carton that was set
aside during unpacking.
2. Remove the mounting screws from the front of the left front caster.
3. Using the mounting screws provided with the bracket, install the hold-
down bracket.
4. Drill the mounting holes and insert the necessary anchoring devices to
accept 3/8” diameter lag bolts.
5. Repeat steps 2 thru 4 for the right rear caster. If the rear of the sterilizer
is not accessible, install the hold-down bracket in the alternate location
shown in Figure 4–24 on page 4–26.