Note: 
When pouring the liquid from the separator, make sure the discharge pipe is at the lower position.Slant at 
an angle not larger than 20° 
Use a transparent container to collect the content inside the separator. Check its color, seal it well and return 
it to the factory for inspection. 
Note: If the compressor is damaged and needs to be replaced, the gas-liquid separator should also be replaced, 
whether or not there are impurities in the separator or other abnormal conditions.   
Confirm which parts of the system should be replaced. Make sure the pipe mouths of the damaged parts or 
components are sealed by adhesive tape as soon as they are detached. Keep them in the original condition for 
future analysis. 
Step 7: Clear the pipeline 
After confirming which parts of the system should be replaced, check the pipeline of the system. Blow 
through the main pipeline with nitrogen. After clearing the pipeline, if the components are not replaced 
immediately, seal the pipeline with adhesive tape to prevent the system from being contaminated by water and 
impurities in the air.   
Step 8: Replace the compressor 
For the removal of compressor, please refer to the section: Removal of Major Components. 
Step 9: Check/Replace the gas-liquid separator 
Note: If a compressor is damaged and needs to be replaced, its gas-liquid separator should also be replaced. 
This is to avoid the abnormal condition of the separator from affecting the safe and reliable operation of the 
system. 
For the removal of gas-liquid separator, please refer to the section: Removal of Major Components. 
Step 10: Check the system for leaks 
(1)   First of all, check each welding point. Check whether the welding points are smooth and whether there is 
any obvious welding hole or other abnormal condition.   
(2)   Next, fill high-pressure nitrogen into the system for leak detection. If it is only the outdoor unit that needs 
to be repaired and the indoor unit is confirmed normal, then it’s OK to charge high-pressure nitrogen into 
the outdoor unit only. Fill in the nitrogen simultaneously from the high pressure side and low pressure 
side. We recommend charging the nitrogen from the big and small valves at the same time. The 
pressure of nitrogen should be above 20kgf. Then use soapy water to check for leaks. Check the 
welding points particularly. 
(3)   Finally, retain the pressure of the system. Fill high-pressure nitrogen into the system and maintain the 
pressure above 25kgf. Close the big and small valves and keep the pressure of indoor and outdoor units