3 Piping work and refrigerant charge
General notes before performing pipe work
SMGB0136 rev.0 - 07/2021
42
3.1 General notes before performing pipe work
3.1.1 Piping Materials
1 In order to avoid supply problems in terms of local regulations and quality, prepare locally-supplied copper pipes.
? NOTE
In case of using copper pipes for piping sections bigger than Ø19.05 mm (3/4 inches), aring work cannot be performed. If necessary,
use a joint adapter.
2 Select the piping size with the correct thickness and correct material able to withstand sufcient pressure.
3 Select clean copper pipes. Make sure there is no dust and moisture inside. Blow the inside of the pipes through with
oxygen-free nitrogen to remove any dust and foreign materials before connecting pipes.
4 After connecting the refrigerant piping, seal the open space between the knockout hole and refrigerant pipes by using
insulation material as shown below:
A. Insulator material.
B. Field-supplied refrigeration pipe.
! CAUTION
• Do not use saws, grindstones or other tools which cause copper
powder.
• When cutting pipes, secure the part for brazing in accordance with
both national and local regulations.
• Use security glasses and gloves for cutting or welding works.
Piping Connection
Fix the connecting pipe as shown in the following gure using the insulation attached to the Indoor Unit.
A. Use the are nut of the indoor unit.
B. Insulate this part with the attached insulation.
C. Fix this part with the attached cord band or with tape.
D. Field-supplied refrigerant piping.
E. Field-supplied insulation.
F. Brazing.
G. Make ares after attaching are nut to the connecting pipe in 
the Multi-kit package.
H. Insulation attached to indoor unit.
I. Indoor unit.
? NOTE
• A system with no moisture or oil contamination will give maximum performance and lifecycle compared to a poorly prepared system.
Take particular care to ensure that all copper piping is clean and dry internally.
• To ensure this, blow oxygen-free nitrogen through the pipes.