Maintenance location Work instructions Interval
Wheels / brakes
Packer and lateral support wheels Check state and fastening
Re-tighten the wheel nuts - see above
Check air pressure
Support wheels 15.0/55 --17 2.6 bar
Packer wheels 210/95 - 24 AS 4.25 bar
prior to use
Bearing for carrying axle journal Check clearance and adjust if necessary (must only be
carried out by an expert workshop)
120 h /
6 months
Brake lines and hoses Check for damage, squashing and kinks prior to use
Air reservoir drain as required
Pipe lter Clean as required
Brake Check condition and function. - correct if necessary prior to use
Safety installations
Road lighting equipment and warning
plates
Check condition and function prior to use
Warning and safety labels Check that they are in place and legible prior to use
At the end of the season
Complete machine Check wear items and replace if necessary
Metering units Dismantle, clean with compressed air and brush - check for damage
Clean the machine Do not spray plastic parts with oil or similar
Piston rods Spray with anti-corrosion oil
Hydraulic hoses
¾ Check the hydraulic hoses regularly for damage (cuts, chang, etc.).
¾ Replace damaged and faulty hoses immediately.
¾ Hydraulic hoses must be replaced after 6 years. For this purpose pay
attention to the manufacturing date on the hose line (year/month) and
on the hose (quarter/year):
Hose line Hose
¾ Depending on the conditions of use (e.g. weather inuences) or in case
of higher strains on the machine the hoses may need to be replaced
earlier.
¾ Have the hydraulic system checked by an expert at least once every year.
¾ In addition follow the country specic regulations and directives.
75