Figure 5-20 Securing a power cable
Step 7 Log in to the iBMC WebUI, and check whether the new component is normal. For details, see
the Huawei Rack Server iBMC User Guide.
----End
5.4.2 DC PSU
To install a DC PSU, perform the following steps:
Step 1 Wear an ESD wrist strap. For details, see 12 Preventing Electrostatic Discharge.
Step 2 Remove the PSU filler panel. See Figure 5-21.
2288H V5 Server