Figure 3-46 Laying out and binding the PGND cable
4. Remove the cut-off ends of the cable ties from the cabinet.
5. Use a Phillips screwdriver to remove the M6 screw on the earthing strip of the cabinet.
6. Use a Phillips screwdriver to fasten the other end of the PGND cable to the ground
terminal on the earthing strip.
Figure 3-47 Fastening the PGND cable
Step 3 Install power cables.
1. Check the power supply type.
If the AC power supply is used, go to Step 3.2.
If the DC power supply is used, go to Step 3.3.