Figure 3-46 Laying out and binding the PGND cable
4. Remove the cut-off ends of the cable ties from the cabinet.
5. Use a Phillips screwdriver to remove the M6 screw on the earthing strip of the cabinet.
6. Use a Phillips screwdriver to fasten the other end of the PGND cable to the ground
terminal on the earthing strip.
Figure 3-47 Fastening the PGND cable
Step 3 Install power cables.
1. Check the power supply type.
– If the AC power supply is used, go to Step 3.2.
– If the DC power supply is used, go to Step 3.3.
E9000 Server
User Guide
3 Installing the E9000