Step 2 Install switch modules or pass-through modules.
1. Completely open the two ejector levers on a switch or pass-through module, and
horizontally insert the switch or pass-through module into the chassis. See (1) and (2) in
Figure 3-25.
Figure 3-25 Installing a switch or pass-through module
2. Completely close the two ejector levers on the switch or pass-through module. See (3) in
Figure 3-25.
3. Use a Phillips screwdriver to tighten the two M3 captive screws on the switch or pass-
through module. See (4) in Figure 3-25.
4. Repeat 1 to 3 to install other switch or pass-through modules.
----End
3.9 Installing a Half-Width Compute Node
During operations, wear protective gloves to prevent personal injury.
E9000 Server
User Guide
3 Installing the E9000
Issue 25 (2019-11-30) Copyright © Huawei Technologies Co., Ltd. 64