3.13 Verifying the Installation
Verifying the Chassis Installation
Verify the chassis installation against the check items in Table 3-2. Rectify any item that does
not meet the requirements.
Table 3-2 Verifying the chassis installation
No.
Check Item Check Result
1 Labels on the chassis are clear and properly pasted. -
2 Screws for securing the chassis are properly installed. -
3 Paint on the chassis is not scraped and the surface is not
stained. Otherwise, apply paint or clean up the stains.
-
4 Filler panels are installed in all vacant slots. -
5 The instruction manual and accessories delivered with the
product are intact.
-
Verifying the Cable Installation
Verify the cable installation against the check items in Table 3-3. Rectify any item that does
not meet the requirements.
Table 3-3 Verifying the cable installation
No.
Check Item Check Result
1 Cables are properly routed in the cabinet, complying with
Huawei's cable layout specification.
-
2 Power cables and PGND cables are properly connected. -
3 PGND cables and power cables are intact without joints. -
4 Power cables and PGND cables are straight and not
coiled.
-
5 Power cables, PGND cables, and signal cables are bound
separately, and the distance between a power cable and a
signal cable and the distance between a PGND cable and a
signal cable meet requirements.
-
6 Cables are not installed above the heat dissipation holes. -
7 Cable ties are evenly spaced and properly fastened. -
8 The bending radius of a cable meets the specifications. -