l Floating nut hook
Auxiliary Materials
l Screws (M6)
l Cable ties
l Fiber binding tapes
l Corrugated pipes
l Floating nuts
Components
l Compute nodes
l Switch modules
l PGND cables
l Ethernet signal cables
l Power cables
l Optical modules
l Optical cables
3.2 Unpacking the Chassis Packing Case
Procedure
Step 1 Check the packaging and the seal on the packing case.
If the packing case is damaged (for example, the packing case is wet or deformed, or the seal or
pressure-sensitive tape is unsealed), preserve onsite evidence and report the actual conditions to the
supplier or Huawei Technologies Co., Ltd.
Step 2 Use a pallet truck to carry the chassis to the equipment room, and remove the pallet truck.
Figure 3-2 Carrying a chassis
E9000 Server
User Guide
3 Installing the E9000
Issue 25 (2019-11-30) Copyright © Huawei Technologies Co., Ltd. 46