Figure 3-42 Installing the full-width compute node
3. Completely open the ejector levers on the full-width compute node. See (2) in Figure
3-42.
4. Horizontally insert the full-width compute node into the chassis. See (3) in Figure 3-42.
5. Close the ejector levers on the full-width compute node. See (4) in Figure 3-42.
----End
3.11 Installing the PGND Cable and Power Cables
NO TICE
l To ensure personal and equipment safety, use the recommended power cables.
l Power cables can be used only for dedicated server devices, and cannot be used for any
other devices.
E9000 Server
User Guide