Workflow
Figure 3-43 Process
Procedure
Step 1 Determine where to connect the PGND cable and power cables.
A maximum of six PSUs can be installed in an E9000 chassis. Figure 3-44 shows the
positions of the socket of PSU 1 and chassis ground terminal.
Figure 3-44 Ground terminal and power supply sockets