Figure 8-35 Opening the valve
Step 9 Check the end pressure gauge on the front of the cabinet. The pointer should be
in the green zone and the pressure reading should be greater than 1.6 MPa at
20°C. Record the reading of the pressure gauge. 8 hours later, observe the pressure
gauge again. The pressure reading should remain unchanged.
----End
FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario) 8 Installing Devices Inside the Pre-fab. Module
Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd. 96