11 Installation Verication
After the FusionDC1000 is installed, you need to verify the installation.
Table 11-1 Post-installation checklist
No. Check Item Check
Method
Expected Result
1 Pre-fab. module
installation
Observe The installation conforms to the
design requirements.
2 Equipment
appearance
Observe The equipment is intact and free
from inclination, distortion, pain
drop, and rust.
All connections are secure.
3 Water pipe
connections
Observe Water pipes are securely connected.
4 Thermal insulation
layers on water
pipes
Observe All pipes are seamlessly wrapped with
thermal insulation layers.
5 External grounding Observe Each pre-fab. module has at least
two ground points and is grounded
securely with a ground resistance
of 10 ohms or less.
Each row of cable trays has at least
two ground points and is grounded
securely with a ground resistance
of 10 ohms or less.
FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario) 11 Installation Verication