4 Installing a Pre-fab. Module
4.1 (Optional) Concrete Platform Scenario
4.1.1 Determining the Pre-fab. Module Installation Position
Prerequisites
The
eld meets site requirements.
Before installing a pre-fab. module, check the height of concrete platforms
and ensure that the height (altitude) error between the upper surfaces of all
platforms does not exceed 5 mm.
CA UTION
Concrete platform levelness is critical to pre-fab. module installation. Ensure that
the concrete platform meet requirements before installing pre-fab. modules.
Context
Before installing a pre-fab. module, determine its installation position and
direction based on site space.
Preparations
Tools: marker, ink foundation, long leather measuring tape
Materials: none
Skill requirement: skilled technician
Procedure
Step 1 Determine the reference points for installing a pre-fab. module on the concrete
platforms. Mark the reference points using a marker.
FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario) 4 Installing a Pre-fab. Module
Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd. 30

Table of Contents

Other manuals for Huawei FusionDC1000A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionDC1000A and is the answer not in the manual?

Huawei FusionDC1000A Specifications

General IconGeneral
BrandHuawei
ModelFusionDC1000A
CategoryStorage
LanguageEnglish

Related product manuals