Figure 4-2 Hoisting a pre-fab. module
Step 2 Use four angle steel brackets to secure the pre-fab. module.
1. Remove the rubber plugs from the pre-fab. module
xing holes using a
Phillips screwdriver.
2. Align the two mounting holes in an angle steel bracket with the two holes on
the pre-fab. module, and mark the hole positions for mounting the angle
steel bracket on the concrete platforms using a marker.
NO TICE
Mark all four mounting holes where each angle steel bracket contacts the
concrete platform.
Place a wooden block on the top of an expansion bolt, and then knock at
the wooden block using a claw hammer to avoid damaging the expansion
bolt.
When you drill a hole using a hammer drill, keep the drill bit perpendicular
to the ground and hold the drill stock
rmly with both hands to prevent
irregular drilling and damage to the ground.
If the ground is too hard and smooth for the drill bit to secure its position,
use a chisel to punch a pit before drilling.
Before you hammer an expansion bolt vertically into a mounting hole,
clean up dust from the inside and surrounding of the hole.
Each angle steel bracket must be secured by two mounting holes.
Preferentially drill the outer two mounting holes. If steel bars in a concrete
platform block the drill bit, drill the inner mounting holes.
FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario) 4 Installing a Pre-fab. Module
Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd. 34