EasyManuals Logo

Huawei FusionDC1000A Installation Guide

Huawei FusionDC1000A
130 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #45 background imageLoading...
Page #45 background image
Figure 4-7 Base installation scenario diagram (unit: mm)
(1) Pre-fab. module base (2) Concrete platform (3) Ground
Step 2 Determine the installation position for the rst base in the installation area based
on the site space, and draw longitude and latitude reference lines between the
rst base and other bases.
NO TICE
Lines should be perpendicular or parallel, with an angle of 90 degrees at cross
points.
The point where the reference lines intersect is the middle point for installing a
pre-fab. module base.
Step 3 Place bases based on the reference lines.
FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario) 4 Installing a Pre-fab. Module
Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd. 38

Table of Contents

Other manuals for Huawei FusionDC1000A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionDC1000A and is the answer not in the manual?

Huawei FusionDC1000A Specifications

General IconGeneral
BrandHuawei
ModelFusionDC1000A
CategoryStorage
LanguageEnglish

Related product manuals