NO TICE
Each base must be secured by four mounting holes. Preferentially drill the outer
four mounting holes. If steel bars in the concrete platform block the drill bit,
drill the inner mounting holes.
Place a wooden block on the top of an expansion bolt, and then knock at the
wooden block using a claw hammer to avoid damaging the expansion bolt.
When you drill a hole using a hammer drill, keep the drill bit perpendicular to
the ground and hold the drill stock
rmly with both hands to prevent irregular
drilling and damage to the ground.
If the ground is too hard and smooth for the drill bit to secure its position, use
a chisel to punch a pit before drilling.
Before you hammer an expansion bolt vertically into a mounting hole, clean up
dust from the inside and surrounding of the hole.
1. Drill mounting holes using a hammer drill.
2. Rotate nuts onto expansion sleeves to prevent the expansion sleeves from
uttering.
3. Knock the expansion bolts vertically into mounting holes until the at
washers are ush with the oor.
4. Remove the nuts, spring washers, and at washers.
Figure 4-9 Installing an expansion bolt (unit: mm)
(A) Nut
(B) Spring washer
(C) Flat washer (D) Wooden block
Step 6 Reinstall the pre-fab. module bases to the concrete platforms with the expansion
bolts securing the bases. Remount the
at washers, spring washers, and nuts on
the expansion bolts and tighten the expansion bolts in sequence using a torque
wrench.
FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario) 4 Installing a Pre-fab. Module
Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd. 40