Page #77 background imageLoading...
Page #77 background image
Figure 8-2 Installing battery modules
(1) Full-capacity cabinet conguration (2) Half-capacity cabinet conguration
NO TE
This section uses full-capacity cabinet conguration as an example to describe how to
install battery modules. The actual conguration prevails.
Step 4 Remove the front covers from battery modules, and install battery bae plates.
Figure 8-3 Installing battery bae plates
NO TE
Place the front covers properly to prevent the light pipes from falling o.
FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario) 8 Installing Devices Inside the Pre-fab. Module
Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd. 70

Table of Contents

Other manuals for Huawei FusionDC1000A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionDC1000A and is the answer not in the manual?

Huawei FusionDC1000A Specifications

General IconGeneral
BrandHuawei
ModelFusionDC1000A
CategoryStorage
LanguageEnglish

Related product manuals