TechDoku_CC1000_VCC1000_CC3000_VCC3000_GenPM_GB_860
25010_86025110.doc
As long as you press this button the material will be pushed up-
wards.
The automatic drawing cycle (draw-pause-reverse) will be switched
on/off with this button.
Allows a complete vacuum build-up with subsequent flooding of the
induction chamber by means of protective gas.
Switching on and off the vacuum pump, when the pump is connected
to the backside socket from the machine.
With enabled printer (light in button is on) starts a casting report print
out at the end of the casting process. For service reasons: you’ll get
full parameter printout when you press button printer for five sec-
onds. Please pay attention to parameters P.118 and P.119.
With pressing this button, the sealing rod opens or close, which let
flow liquid material in the die or granulation tank when it is requested.
With software state 800.0104 and higher (see service info page 1), a
safety system is installed, which monitors a swivelled out granulating
tank. You can deactivate the warning W077 by pressing the button
‘sealing rod’ for 3 seconds. This is useful when you want to clean an
empty warm crucible, but the granulating tank is swivelled out.
7.4 Casting
7.4.1 Overview
For continuous casting please install die cooler and drawing unit.
For granulating install granulation tank.
For sinter process please install sinter-unit.
7.4.2 Continuous casting
Preparation with drawing of sheet and wire
Before starting check chambers, crucible and crucible shield for dirt, residues or
possible damage. It is recommended to use a vacuum cleaner for the entire in-
ductor housing. The sinter filter (left side of the sealing rod) should be twisted out
and cleaned with compressed air.
With using of compressed air wear a dust proof
mask and must not blow in the room.