Commissioning
Test commissioning
Target of the "test commissioning"
For test and demonstration purposes, the motor is to start to rotate with as few wiring and
settings as possible in best time.
Keypad control or terminal control
First decide how the controller is to be controlled during test commissioning:
Test commissioning with keypad control
( 28)
Test commissioning with terminal control ( 30)
Tip!
The operation and commissioning of the internal keypad is described in the
Hardware Manual of the 8400 frequency inverter. The index of the CD attached to
the device as scope of supply contains the Hardware Manual saved as PDF.
A detailed description of how to use the integrated keypad can be found in this
manual in the chapter
Parameter setting and diagnosing directly at the controller
( 21)