CHAPTER 2 INSTALLATION
– 82 – NWA-008841-001 Rev.5.0
90ch2001.fm
INSTALLATION OF MAIN EQUIPMENT
Floor Standing Installation
Check the site for installing the PBX with the work drawing to verify that the
required floor space is ensured and that service entrances and ducts for trunk/
extension cables, power cables and bus cables have been properly worked at
correct positions. See “Floor Space” and “Cable Hole Location”.
Page 84, Page 85
Mark positions for installation of the PBX main equipment.
For Fixed Equipment, detach the BASE PLATE from the BASE. See “Floor
Marking for BASE PLATE”. Page 86
For Stationary Equipment, see “Floor Marking for BASE TRAY”.
Page 86
NOTE: Measure the level of the floor surface before installing the PBX main
equipment.
Check the level of the floor. If necessary, adjust the level by inserting spacers
beneath the equipment.
First open necessary number of preliminary prepared holes using the drill bit
for small-diameter holes, then use the finishing drill bit for finishing drill holes.
See “Drilling”. Page 87
Detach the front cover of each Module. See “Detaching FRONT COVER”.
Page 88
Continued on next page
Start
Checkup
before installation
Marking
Leveling
Detaching Front Cover
Drilling
A
INSTALLATION OF MAIN EQUIPMENT

Table of Contents

Other manuals for NEC NEAX 2000 IPS

Related product manuals