6.1. FREQUENCY OF OPERATIONS
Maintenance schedule
Frequency of operations
Operations
Each time
the tool
is used
1
Every 4
hours
Every week After use
Visually check the general condition of the tool.
See 6.3.1. Visual check of the general condition of the
tool, page 32.
X
Check the functioning of the Activ' Security.
See 6.3.2. Checking the operation of the Activ'Security
and the conductivity of the gloves, page 33.
X X
Check the condition of the gloves and their conductiv-
ity.
See 6.3.2. Checking the operation of the Activ'Security
and the conductivity of the gloves, page 33.
X X
Check the operating trigger.
See 6.3.3. Checking the operating trigger, page 34.
X
Check the crossing over of the hook and the blade.
See 6.3.4. Checking the crossing over of the hook and
the blade, page 35.
X
Check the sharpness of the blade.
See 6.3.5. Sharpening the blade, page 37.
X
Check the tightness of the blade.
See 6.3.6. Adjusting the tightness of the blade, page
38.
X
Check the tightness of the tool power cord.
See 4.7. Connecting the tool to the ULIB 150P and 250
batteries, page 17.
X
Check the battery charge level. X X
Changing the blade kit
See 6.4. Changing the blade or pins, page 38.
EVERY 200 HOURS or as necessary to main-
tain good quality cutting, replace the blade.
Grease the blade.
See 6.5. Greasing the blade, page 41.
X
Clean the tool (blowing or brushing, not high pressure
jet cleaning).
See 6.6. Cleaning the tool, page 41.
X
31