EasyManua.ls Logo

PoolPak MPK series - Inspection; Unit Hookup; Gas Furnace Auxiliary Heat Option; Power Supply

PoolPak MPK series
88 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
© 2017 PoolPak LLC. All rights reserved. MPK Series - Installation, Operation and Maintenance | 31
PoolPak
®
MPK Series IOM
For ground-level installation, a one-piece concrete slab with footers that extend below the frost line is highly
recommended. Additionally, the slab should not be tied to the main building foundations to prevent noise
transmission. The unit must be supported with adequate space to allow for a condensate line trap.
For roof-top installation, choose a location with adequate structural strength to support the entire weight of the
unit and service personnel. For non-curb mounted units, provide spring vibration isolation to minimize vibration
transmission to the roof structure. The unit must be situated with adequate height for a condensate line trap. The
PoolPak unit may be mounted on equipment rails with spring vibration isolation. For any alternative mountings not
discussed here, contact the factory for additional guidance. Care must be taken not to damage the roof. If the roof
is bonded, consult the building contractor for allowable installation procedures.
Inspection
Immediately upon receiving the unit, inspect it for damage which may have occurred during transit. If damage is
evident, note it on the carrier’s freight bill. A written request for inspection by the carrier’s agent should be made at
once.
Unit Hookup
Avoid tearing or damaging unit insulation while working on or around the unit. Do not stack access panels. Stand
them upright with the insulation away from traffic.
GAS FURNACE AUXILIARY HEAT OPTION
When using a gas furnace, power venting is provided for all unit sizes. External vent piping and/or cap is required.
Please refer to the furnace manufacturer’s manual for piping and venting instructions. Install, leak-test, and properly
regulate piping for the gas-fired heater. Pressures should be regulated to the entering pressures as shown on the
furnace manufacturer’s data plate or manual.
POWER SUPPLY
The contractor is required to supply (unless supplied as an option by PoolPak) and install separate fused
disconnect(s) within easy accessibility of the PoolPak unit. Use the minimum circuit capacity listed on the unit’s
data plate to determine the minimum wire size for incoming electrical power. The ground connection for the unit
is located in the unit control panel. The power supply to the unit must be adequate for the compressor starting
amperage (LRA). All field wiring must be done according to the wiring diagram provided with the unit and in
conformance to the National Electrical Code (NEC) and any other applicable local electrical code. Conduits
connected to outdoor units must be sealed in accordance with NEC 300.7 (A)
If a remote air-cooled condenser is required, a separate power feed must be provided for the air-cooled condenser.
When the auxiliary electric heater option is provided, another power connection point is provided in the electric
heat compartment. This power connection feeds the auxiliary electric heating coil. With this option, the contractor is
required to supply and install a second fused disconnect.
PoolPak MPK units are available in single and dual point power supply options. The 208V option is dual point
power only. See illustrations.

Table of Contents

Other manuals for PoolPak MPK series