6 Assembly and commissioning
6.1 Installation location requirements
Requirements at the installation location
Consider space and statical requirements such as load capacity of
ceilings, etc. at the intended installation location.
Temperatures at the installation location of the inlet isolation
device should not fall below 14°F (-10°C) and not exceed 140°F
(60 °C).
Q-FlapCompact II/Plus is certified for pull/flow applications. The
inlet isolation device should be installed in the following order (in
flow direction):
Inlet isolation device
- filter
(container) - fan.
Filter (Container)
Fan
Q-FlapCompact II/Plus
Direction of Flow