Roche Diagnostics
E-60 Operatorโs Manual ยท Version 3.1
14 ISE maintenance Cedex Bio System
ISE maintenance actions
12
Slide off the lid of the fluid distributor.
13
Disconnect the tubing from the electrode block.
o Open the electrode block lid.
o Release the tension lever.
o Lift the connector on the side of the K electrode.
o Disconnect the tube on the side of the tension lever.
o Lift the connector to the ISE Reference Electrode and disconnect the tube
leading to the ISE Reference Solution bottle.
14
Disconnect the tubing connecting to the peristaltic pump.
Removing the tubing
15
Lift the tubing from its routing, follow carefully the individual tubes.
16
Dispose of the tubing. Treat it as biohazardous waste.
Installing the new tubing
17
Install and connect the tubing in the order recommended on the illustration on
the ISE tubing set cover.
When installing the single items, perform the individual steps in reverse order of
removing the items.
A Lid of fluid distributor
Figure E-14
A Tension lever
Figure E-15