Mounting and Commissioning 3
This chapter is intended for experienced commissioning staff. He must be familiar with the commissioning of
protection and control systems, the management of power systems and the safety rules and regulations. Hard-
ware adjustments to the power system data might be necessary. The primary tests require the protected object
(line, transformer, etc.) to carry load.
3.1 Mounting and Connections 286
3.2 Checking Connections 306
3.3 Commissioning 312
3.4 Final Preparation of the Device 332

Table of Contents