Initial installation and adjustments
04_Initial_installation_en.fm - V 0.1 - 14.4.11
33 / 187
4
34
4 Initial installation and adjustments
4.1 Initial familiarization
The machine must only be operated by properly trained and instructed
personnel. For this purpose a corresponding instruction session and training is
conducted when the machine is handed over.
4.1.1 Handing over the machine and instructing the operator
The following checklist should be followed when handing over the machine to
the operator:
Operating
instructions
Go through the Operating Instructions (page by page) and explain them in
detail through practical training on the machine.
Items which are particularly important include:
Accident Prevention Regulations published by the employer’s liability
insurance associations in the users country
Technical data
Operator controls, indicating and warning elements
Checks before putting the machine into operation
Engine running-in instructions
Starting and shutting down the engine
•Driving
Recovery and transport of the machine
Operation of all functions
Explanation of maintenance intervals and points according to
Maintenance and Inspection Plan by demonstrating and explaining
maintenance points on machine
Lubrication intervals and points of lubrication according to lubrication chart
and demonstration of these points on the machine
Spare parts list
Explain the structure of spare parts list, figures and the associated texts.
Explain that spare parts orders must always be accompanied by machine
type, vehicle identification number ("Fz-Id.Nr."), parts designation, complete
spare part number, quantity, delivery address, etc.
Warranty
Explain the warranty conditions.
Explain the inspection cards with a hint to the maintenance and inspection
plan.
Fill in the warranty/handing over card correctly and send it back to us.
Note
Initial inspection must be carried out before commissioning. See chapter 6.6
"Maintenance and Inspection Plan", page 60.