Trane Optimus RTHD - Testing, Refrigerant, Load Conditions, and Heaters; Equipment Room and Owner Awareness Checks

Trane Optimus RTHD
92 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
RTHD-SVX01L-EN
87
All controls installed and connected
6. Testing
Dry nitrogen available for pressure testing
Trace gas amounts of R-134A or R-513A available
for leak testing, if necessary
7. Refrigerant on job site
8. Systems can be operated under all actual load
conditions
9. Heaters
Energize oil sump and compressor heaters and
verify they are operational using a temperature
probe
If unit was factory charged (model number digit 35
= A or C), energize heaters for 24 hours prior to
start-up.
Important: It is required that heaters are energized
for a minimum of 24 hours prior to
start-up. Therefore, chiller should have
power for this amount of time before
Trane Service arrives to do start-up.
If unit has nitrogen charge (model number digit 35 =
B or D), contact Trane Service for unit charging
prior to start-up
10. Equipment room
Does the equipment room have a refrigerant
monitor/sensor capable of monitoring and alarming
within the allowable exposure level of the
refrigerant?
Does the installation have properly placed and
operating audible and visual refrigerant alarms?
Does the equipment room have proper mechanical
ventilation?
If it is required by local code, is a self-contained
breathing apparatus available?
11. Owner awareness
Does the owner have a copy of the MSDS for
refrigerant?
Note: Additional time required to properly complete the
start-up and commissioning, due to any
incompleteness of the installation, will be invoiced at
prevailing rates.
This is to certify that the Trane® equipment has been
properly and completely installed, and that the applicable
items listed above have been satisfactorily completed.
Important: It is required that the chiller heaters are
energized for a minimum of 24 hours prior to
start up. Therefore, the chiller should have
power for this amount of time before Trane
Service arrives to do start-up of the
equipment.
Checklist
completed by: _____________________________
Signed: _____________________________
Date: _____________________________
In accordance with your quotation and our purchase order
number __________________, we will therefore require
the presence of Trane service on this site, for the purpose
of start-up and commissioning, by __________________
(date).
Note: Minimum two-week advance notification is required
to allow scheduling of the chiller start-up.
Additional comments/instructions:
Note: A copy of this completed from must be submitted to
the Trane Service Office that will be responsible for
start-up of chiller.
Optimus™ Chiller Installation Completion Check Sheet and Request for Trane Service