Series R Start-up Test Log
Job Name Job Location
Model # Serial # start date:
Sales Order # ship date: Job elevation (ft. above sea level)
STARTER DATA: START-UP ONLY
Manufacturer Chiller appearance at arrival:
Type: (solid state, wye-delta)
Vendor ID #/Model #:
______Volts _______Amps ______ Hz Machine Gauge Pressure: psig
COMPRESSOR DATA: Machine UCP2 Pressure psig
Model #:
Complete if pressure test is required
Serial #: Vacuum after leak test= mm
NAMEPLATE DATA: Standing vacuum test = ________ mm rise in ________ hrs
____________ RLA ____________KW
____________Volts 50 60 Hz
UNIT CHARGES
DESIGN DATA: Unit refrigerant charge: lbs R -
____________ RLA ____________ KW
____________Volts 50 60 Hz
Unit Oil Charge: gal oil
CURRENT TRANSFORMER SUMMARY OF UNIT OPTIONS INSTALLED
Part Number (“X” code and 2-digit extension) Y N Tracer Communications Interface
Primary CT’s Y N Options Module
X - Y N Outdoor Air Sensor
X - Y N Ice Making Control
X - Y N Other
DESIGN CONDITIONS
Evap Design: ________GPM _________ PSID Ent. Water F__________ Leaving Water F_________
Evap Actual: ________GPM _________ PSID Ent. Water F__________ Leaving Water F_________
Cond Design: ________GPM _________ PSID Ent. Water F__________ Leaving Water F_________
Cond Actual: ________GPM _________ PSID Ent. Water F__________ Leaving Water F_________
Owner Witness Signature: ______________________________________________________________________