Tyco Electronics Galaxy SC Controller J85501F-1
Issue 13 February 2001 Acceptance Testing 5 - 13
also verify that this LED activates during these tests for the bay in which
the alarm originates (and not in any other). For GPS cabinets, the alarm
lamp of the cabinet containing the controller will always activate, in
addition to the cabinet containing the alarm.
Minor Fuse Alarm Minor Fuse Alarm may be tested by placing a blown fuse in the alarm
fuse position of the plant Capacitor Charge circuit (if equipped) or by
inserting a paper clip into the alarm indicating hole of its fuse holder.
Alternately, replace one of the unused regulation fuses of the BJF fuse
termination board with a blown GMT type fuse. In either case, the MIN
and either DIST or RECT panel LEDs will activate, along with the
Power Minor and MNF alarm relays.
Modem/Data
Switch
If the Modem (L-AE) and/or Data Switch (L-AH) options have been
provided, they can be tested after wiring and configuration is completed
by dialing into the modem port and, if equipped, passing through to the
devices wired to the equipped Data Switch ports. Refer to Section 6 for
the T1.317 Data Switch commands required.
Remote
Peripheral
Monitoring
If the Remote Peripheral Monitoring option (L-AG) and J85501G1
monitoring units have been equipped, each channel configured should
be tested for accuracy with a clamp-on ammeter (for Shunt Monitor
channels), voltmeter (for Voltage Monitor channels), or thermometer
(for Temperature channels). If alarms have been configured through the
use of User Defined channels, they may also be tested by adjusting their
program line to move the thresholds or by adjusting the channel
programming to change the value reported for the channel. Refer to
Section 7 for complete feature descriptions of each of these optional
monitoring devices.
Rectifier
Sequencing
If Rectifier Sequencing in an Intelligent controller has been enabled (via
EasyView path: Main → Configure → Rectifiers, testing can be
completed by temporarily using a shorting clip across TB3 position
12-13 (ETR/ETRR) terminal block on the BLG1 board. This will cause
all rectifiers configured for Rectifier Sequencing control to shut off.
Releasing this clip will then cause the rectifiers to restart sequentially in
the manner in which they have been programmed.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Tyco Galaxy SC Controller and is the answer not in the manual?

Tyco Galaxy SC Controller Specifications

General IconGeneral
BrandTyco
ModelGalaxy SC Controller
CategoryController
LanguageEnglish

Related product manuals