Appendix C _____________________________________________ Installation and Test Procedures
VAISALA______________________________________________________________________ 365
C.3 Power Up Check
Test Goal
Verify that the RVP901 and RVP902 properly powered up.
Test Procedure
The display terminal of the RVP902 shows summary power up messages.
1. Apply power to the RVP902 (or reset it) and the RVP901.
2. Verify the following:
Test Passed
When power is applied to the RVP901, the red and green lights blink
and then stay on.
When the CAT5E cable is disconnected from either the RVP902
server or RVP901, the red light remains on and the green light turns
off.
For Customer_________________________________ Date__________
For Vaisala___________________________________ Date__________