VERSION 06/2014 ORDER NUMBER DOC2329371
Section Type of inspection Requirements Inspection by Type of inspection Inspection
interval
1 Resistance to ground of work
piece's locating point
The resistance to ground of
every work piece's locating point
must not exceed 1 megohm
(measurement voltage must be
1,000 V). The design of the work
piece receiver must ensure that the
adapters remain grounded during
coating.
CP ME/CI
Measure resistance to ground
(work piece receiver - ground
potential)
max. 1 megohm @ 1,000 V.
weekly
2 Interlock between technical
ventilation and high-voltage,
compressed air and coating product
supply
The technical ventilation should
be interlocked such that the high-
voltage cannot be switched on
while the technical ventilation is not
working e ectively.
CP FI
Test whether the system is safely
stopped and the product supply,
supply air, and high-voltage
are switched o when the
ventilation is shut down.
annually
3 Inspection of the electrostatic
manual spray equipment for
damage
Electrostatic manual spray
equipment may only be operated
in an intact condition, damaged
devices must be decommissioned
immediately and repaired.
CP FI
Inspect and test
(e.g., by measurement) whether
all parts carrying high-voltage
do not result in discharge which
puts people at risk.
weekly
Legend:
MA = Manufacturer
EM = Employer
SP = Skilled person
FSE = Fire safety engineer
ELC = Electrician
TP = Trained person
FI = Function inspection
ME = Measurement
SI = Standard inspection
VI = Visual inspection
CI = Continuous inspection
TI = Technical inspection