146 Installation checklist
If the drive has not been powered (either in storage or unused) for over one year: The electrolytic DC
capacitors in the DC link of the drive have been reformed. See Capacitor reforming instructions
(3BFE64059629 [English] (available in the Internet or from your local ABB representative).
All protective ground conductors have been connected to the appropriate terminals and the terminals
have been tightened (pull the conductors to check).
The supply voltage matches the nominal input voltage of the unit. Check the type designation label.
The power cables have been connected to the appropriate terminals, the phase order is right, and
the terminals have been tightened. (Pull the conductors to check.)
Appropriate AC fuses and main disconnector have been installed.
The control cables (if any) have been connected to the appropriate terminals, and the terminals have
been tightened. (Pull the conductors to check.)
The control units have been connected to the supply/inverter modules.
There are no tools, foreign objects or dust from drilling inside the cabinet.
All shrouds and covers are in place. Cabinet doors have been closed.
Make sure that...